Client Name: Fletcher Construction Engineering
Project Value: $15M
Location: Ellerslie Panmure Highway
Completion Date: December 2013
Construction of a new fully glazed concourse building straddling twin tracks and a bus station. Facilities include staff and public amenities, 4 escalators and 2 lifts providing access to the track located in a 7m deep trench. Extensive use of high quality finishes including FunderMax cladding, basalt and blue stone tiling, glazed canopies and a live green wall. Complex services required including CCTV, PA and fire systems, and mechanically controlled louvres for temperature control.